Book a building control site inspection

Book a site inspection

Building regulations require that any person carrying out building work should notify us at certain stages of the work.

The stages are set out below for different types of work.

Required notifications of building works
Extensions and new buildingsLoft conversions, internal alterations etc
Commencement (24 hours notice required) Commencement (24 hours notice required)
Foundation excavated (before concreting) Before covering any steelwork/beams
Damp proof course (DPC) Insulation
Oversite (before concrete is laid) Work completed (three days notice required)
Drains in trench (before covering over)  
Drains backfilled (to be tested)  
Before covering any steelwork/beams  
First floor construction  
Roof structure  
Occupation (commercial work only, if occupied before completion)  
Work completed (three days notice required)  

Completion certificate

Make sure you have received your completion certificate prior to making your final payment to your builder. The completion certificate will be required for any future sale of the property.

We reserve the right not to issue a completion certificate if you have failed to notify us for inspections in accordance with the guidance given above.